|
|
|
|
|
The Neo-Classical features of the brick and terra cotta Armitage station are evident in this October 11, 2002 view looking northwest at the historic building. The old-fashioned lights on the station are attractive, but not original (they are, in fact, a bit out of scale with the building's features). The doors and window frames were recently refinished. For an enlarged view, click here. (Photo by Graham Garfield) |
Armitage
(2000N/1000W)
Armitage Street and
Sheffield Avenue, Lincoln Park
Service Notes:
Brown Line: Ravenswood
Purple Line: Evanston Express
Quick Facts:
Established: June 1, 1900
Address:
944-46 W. Armitage Avenue (main entrance [CLOSED FOR RENOVATION])
941 W. Armitage Avenue (temporary entrance)
Original Line: Northwestern Elevated Railroad
Previous Names: Center Street
Rebuilt: n/a
Skip-Stop Type:
Station (1949-1983)
Station (1983-1995)
Status: In Use, Under Renovation
History:
The path of the initial Northwestern Elevated Railroad line, from Lake and Wells Streets to Broadway and Wilson on the what was then the far north side, was cleared in 1895 and erection of the steel was begun January 23, 1896. Several financial difficulties delayed construction several times, a few times necessitating extensions of the company's franchise. All night shifts were eventually required to complete the structure on Christmas Day 1899, days before their deadline to begin service. But Center Street (Armitage's original name) and most of the other stations were incomplete December 31 and, after some finagling, another extension was obtained. Center was completed in early 1900.
Armitage station opened in June 1900 as part of the original stretch of the Northwestern Elevated. The headhouse was one of several stations built from a design by William Gibb on what is now the Brown Line. Architecturally, it is similar to those still at Chicago, Sedgwick, Belmont, Fullerton, and others. Constructed entirely of brick with terra-cotta trim, the Classical Revival design was inspired by the work of the great 16th century Italian Renaissance architect Andrea Palladio1. The bold modeling of the details, especially the columns and segmented arched windows, is characteristic of Italianate work of the late 19th century. The interior featured plaster walls with extensive wood detailing in the door and window frames, ceiling moldings, and tongue-in groove chair rail paneling. Nearly all of this detail remains today, and was recently stripped of its layers of paint and refinished. The original fare collection booth has been replaced.
The dual side platforms at Armitage are covered in the center by two peaked-roof canopies of steel support with a gently-curved bracket and intricate latticework, covered by a corrugated metal roofing. Originally, these covered about half the platform length, but the platforms were subsequently lengthened multiple times to allow longer trains to berth. Many sections of the original platform area still has original railing, which consisted of tubular railings and posts with panels of decorative, vaguely diamond shaped metalwork inside. The platform extensions have plain wooden railings.
Under the initial Northwestern Elevated configuration, Armitage, whose platforms are on the outer tracks, was a local station, inaccessible by the expresses utilizing the inner tracks. After the State Street Subway opened in 1943 and the route configurations were overhauled in 1949, Armitage became a station on the Ravenswood Line, initially serving only "A" trains under the skip-stop express scheme, but eventually called at by all trains.
An interlocking tower was added over the inbound platform in the early 1940s to observe and control the new crossovers at the entrance to the State Street Subway. Armitage Interlocking is no longer controlled from Armitage Tower, however. Armitage Tower was turned into field offices, first for the North District transportation section and later for the Signal Department.
Brown Line Capacity Expansion Project
|
This aerial artist's rendering shows the platform-level design for the renovated Armitage station. The original, historic canopies will remain in place and be refurbished, with elevators added next to them. For a larger view, click here. (Image provided courtesy of the Chicago Transit Authority) |
As a result, the CTA® decided to plan for the Brown Line Capacity Expansion Project, the largest capital improvement project undertaken by the CTA® at the time (surpassing even the Douglas Renovation Project, which was the largest up to that point). The main objectives of the Brown Line Capacity Expansion Project are to expand the line's overall ridership capacity by lengthening station platforms to accommodate eight rather than six-car trains, rehabilitate rail infrastructure and stations, provide for station enhancements to meet the accessibility requirements of the Americans with Disabilities Act (ADA), and upgrade or replace traction power, signal and communication equipment. By far, the largest part of the Brown Line Capacity Expansion Project was the station renovations. Of the Brown Line's 19 stations, only one (Merchandise Mart) was not touched at all due to its modern construction (1988) and ability to berth eight-car trains.
On April 13, 2004, the CTA® announced that it had officially received a Full Funding Grant Agreement (FFGA) from the Federal Transit Administration (FTA). However, in May 2004, CTA® received construction bids for the project that substantially exceeded the budget. As such, the Chicago Transit Board voted on June 9, 2004 to reorganize the project into several discrete pieces to help attract more competitive construction bids. Station renovation work was modified and grouped into five separate packages according to location to help reduce the overall cost of station construction. Armitage station was grouped with Sedgwick, and Chicago in a bid package, all of which were designed by the same consultant, Gonzalez Hasbrouck Architects. Station designs were also revised to reduce costs. Most changes concentrated on non-customer areas such as reducing the size of janitor closets, employee restrooms, electrical rooms and communication rooms. Other areas that were studied for cost reduction were standardizing common station elements, the use of less expensive materials, canopy designs and coverage, and temporary station closures to provide contractors better access to the sites.
|
This artist's rendering shows the street-level design for the renovated Armitage station. The historic station house will be renovated with an addition built behind and next to it. The historic platform canopy is visible at platform level above. The Brown Line-standard railings and modern lights shown here have since been revised to retain and fill-in the historic railings and to use more sympathetic light standards. For a larger view, click here. (Image provided courtesy of the Chicago Transit Authority) |
The 1900-built historic station house will be preserved and restored in the new facility, but also expanded with a new addition built behind and next to it. The new expanded station houses will be larger, with more turnstiles and farecard vending machines. New, wider stairs and elevators will take customers to the boarding platforms.
The platforms will be renovated with new decking, lighting and signage. The existing original, historic canopies will be retained and refurbished. Historic railing sections will be retained. An auxiliary rotogate exit will be provided on the south side of Armitage Avenue.
Other improvements include new fare equipment, signage, electrical, communications, and HVAC equipment; new shelters, customer heaters and benches on the platforms; and a state-of-the-art announcement system.
During station construction, Armitage, Sedgwick, and Chicago will remain open on weekdays, but may experience up to six weekend closures during the construction period when all three stations will be closed at the same time to allow construction crews unlimited access to station platforms.
Work at Armitage station contract began in autumn 2006. Early work included preparatory work at the station site, as well as work at 939 W. Armitage, a historic building adjacent to Armitage station on the east side of the station on the south side of Armitage Avenue. The masonry building with an ornamental front facade is a contributing structure in the Armitage-Halsted Historic District and thus was required to be at least partially preserved. However, the new, expanded northbound platform must occupy part of the footprint of the building. So, the west half of the building was demolished and the east half preserved, with a new west elevation built to enclose the building and allow it to continue to be used, similar in fashion to how the backs of several buildings were removed for the construction of the State Street Subway incline in the same area during the early 1940s. During autumn, crews demolished the interior of 939 W. Armitage, preparing for the demolition of the west half of the building.
Also during autumn 2006, crews installed the new steel stringers for the extended platforms, beginning at the far south end of the platforms and working north. Only the southernmost hundred feet or so were initially installed, with the wood decking applied to these sections beginning the last week of December 2006.
|
Diesel locomotive S-503 and three flatcars with dumpsters load up debris from the adjacent 939 W. Armitage building -- being partially demolished to make way for the extended northbound platform -- during the first south-end "linecut" on December 12, 2006. For a larger view, click here. (CTA Photo) |
Installation of additional stringers, joists, and decking for the platform extensions did not resume until spring 2007. By the end of April, the stringers had been installed all the way to the south end of the existing southbound platform, with decking covering most of that length. Steel had also begun to be set for the auxiliary exit stair from the southbound platform to the south side of Armitage Avenue.
Also during spring 2007, crews began erecting a temporary entrance on the south side of Armitage Avenue, in the location of what will ultimately be an auxiliary exit, to allow the main entrance at Armitage to close for renovation. During March 2007, a temporary wooden station house was constructed, consisting of a simple wood frame structure with plywood walls and a flat, slanted roof. Inside, a Customer Assistant booth was built-in as a room with windows and a door to interact with customers occupying the southeast corner of the interior. The building sat dormant for several months as other work continued.
A second linecut was performed at the south end of the Brown Line during the first weekend of May 2007. However, unlike the first south-end linecut in December 2006, trains were allowed to service Armitage station, terminating at the southbound platform, changing ends, and then returning back to Kimball. Trains were crossed back to the northbound track through Armitage Interlocking. With no rail service to Sedgwick, Chicago, and Merchandise Mart stations from Friday night, May 4 through the end of the Sunday, May 6 service day, bus shuttles operated from Fullerton to Clark/Lake. During the May linecut, crews erected the steel frame for the northbound platform elevator tower, removed the old, narrow wooden platform at the south end of the northbound platform and installed new steel stringers and joists to connect the new platform extension already built south of the station to the existing full-width platform over Armitage Avenue. When the station reopened Monday morning, May 7, the north end of the southbound platform utilized part of the newly-built full-width platform.
|
One of several pre-assembled stair sections -- this one being the top flight of stairs of the auxiliary exit from the northbound platform -- is being lowered into place by crane on May 21, 2007. For a larger view, click here. (Photo by Graham Garfield) |
In late May, crews began installing masonry walls around the steel elevator tower frame that had been erected during the linecut a few weeks earlier. First cinder block was installed, then the surfaces were clad in black tiles. Masonry work continued into mid-June.
During June, work accelerated to prepare the new platforms and the temporary entrance for service. During mid-June through July, work continued to install new permanent railings at south ends of the new platform extensions and around the new auxiliary stairs. Crews installed the canopy over southbound auxiliary stairway and continued to install railings, grilles, windbreaks, and other platform fittings. In late June, the sidewalks for temporary station entrance were poured.
|
The temporary entrance to Armitage station, a simple wood-frame structure on the south side of Armitage Avenue opposite the main entry, is seen looking southeast on opening day, July 23, 2007. For a larger view, click here. (Photo by Tony Coppoletta) |
A week later, on Sunday, July 22, the fare equipment from the old Armitage station house was relocated to the temporary station house across the street. Bus fareboxes were temporary used while the turnstiles were disconnected and moved. At 5am, Monday, July 23, 2007, the temporary station entrance on the south side of Armitage Avenue came into use. Passengers access the platforms via the new auxiliary stairways installed during the previous two months. The old station house was fenced off and the stairs down from the platforms to old station house were barricaded. A new barrier was placed between the stairs on the old section of platform, taking another 100 feet or so of the old platform pout of service. Additional signage and platform furniture was relocated to the new platform. The temporary entrance is expected to be in place through early 2008.
With passengers relocated to the new platforms and temporary entrance, work accelerated on the new facilities on the north side of Armitage Avenue. In mid-July, crews begin selective demolition of the historic station house and demolition of the north- and southbound platforms north of canopies. In early August, the new, permanent station name signs were installed on the newly-opened south platform extensions, replacing the old KDR station name signs that the contractor had temporarily mounted on the new backer plates with a temporary wooden mounting bracket .
The project's Full Funding Grant Agreement with the federal government requires that the CTA® complete the project by the end of 2009.
|
Armitage station, seen looking north from the south end of the outbound platform on May 10, 2003, is a well-preserved example of the Northwestern Elevated's local stations. Both canopies and much of the railing system remains intact and in good condition. The station fits in well with the historic district in which it's located. An inbound Brown Line train is pulling into the station, past the interlocking tower that was added in 1943. For a larger view, click here. (Photo by Graham Garfield) |
![]() |
armitage01.jpg
(50k) |
|
|
cta6158.jpg
(118k) |
|
|
cta53c.jpg
(127k) |
|
|
cta2401.jpg
(127k) |
|
|
armitage02.jpg
(133k) |
![]() |
tour99b.jpg |
|
|
tour01@Armitage01.jpg
(129k) |
|
|
tour01@Armitage02.jpg
(38k) |
|
|
cta2611b.jpg
(100k) |
|
|
cta2829.jpg
(102k) |
|
|
cta3324.jpg
(123k) |
|
|
armitage03.jpg
(187k) |
|
|
armitage14.jpg
(168k) |
|
|
armitage15.jpg
(212k) |
|
|
armitage16.jpg
(200k) |
|
|
armitage17.jpg
(169k) |
|
|
armitage07.jpg
(179k) |
|
|
armitage09.jpg
(243k) |
|
|
armitage10.jpg
(200k) |
|
|
armitage11.jpg
(198k) |
|
|
armitage12.jpg
(170k) |
|
|
armitage18.jpg
(184k) |
|
|
armitage19.jpg
(159k) |
|
|
armitage20.jpg
(180k) |
|
|
armitage21.jpg
(159k) |
|
|
939armitage01.jpg
(126k) |
|
|
armitage23.jpg
(164k) |
![]()
|
|
Notes:
1. Bach and Wolfson, A Guide to Chicago's Train Stations, 222.